Thumbnail for 'Looking along upstream face of embankment'
Format:
Image
Looking along upstream face of embankment from right abutment. Slope is ready for riprap. Note trench at toe of slope to support the riprap.
Thumbnail for 'Looking toward right abutment along upstream face of embankment'
Format:
Image
Looking toward right abutment along upstream face of embankment. Tractor is lowering loaded truck down the slope at station 9+00.
Thumbnail for 'Looking toward right abutment along upstream toe of embankment'
Format:
Image
Looking along upstream toe of embankment toward right abutment from station 7+35. Dragline is excavating a shoulder at toe of slope to support dumped riprap.
Thumbnail for 'Close-up of test pit wall'
Format:
Image
Close-up of one awl of test pit excavated in No. 1 zone of embankment at station 22+25, 97 feet upstream from axis of dam. Purpose of pit was to determine percentage of plus 5-inch stones remaining in materials.
Thumbnail for 'Dumping material on embankment'
Format:
Image
Twelve yard Euclid bottom-dump truck dumping material on the upstream No. 2 section of the embankment at sta. 24+84. this material is approximately 1.5% below optimum moisture. Note the excellent condition of the embankment for truck travel.
Thumbnail for 'Compacting embankment material'
Format:
Image
Sheeps-foot roller compacting upstream No. 2 material at station 20+25, 30 ft. upstream from dam axis. The moisture content of this material is approximately 1.5% below optimum moisture.
Thumbnail for 'Looking toward left abutment from stair shaft'
Format:
Image
Looking toward left abutment from top of stair shaft at 37+00, 20 ft. upstream from axis, showing different types of soil used in fill.
Thumbnail for 'Truck dumping riprap on upstream slope'
Format:
Image
Truck dumping riprap on upstream slope of dam near station 23+50.
Thumbnail for 'Looking toward left abutment along upstream face'
Format:
Image
Looking along upstream face of dam toward left abutment from station 24+00. Bulldozer is being used to place riprap after being dumped from trucks. Note small average size of pieces compared with hat in foreground.
Thumbnail for 'Dumped riprap on upstream face'
Format:
Image
Dumped riprap on upstream face of embankment in the vicinity of station 20+00.
Thumbnail for 'Dumping riprap on top of embankment'
Format:
Image
Dumping riprap from bottom dump Euclid near the top of existing embankment.
Thumbnail for 'Bulldozer placing riprap'
Format:
Image
Placing riprap with bulldozer after truck has dumped.
Thumbnail for 'Looking toward right abutment along cut-off trench'
Format:
Image
Looking toward right abutment in cut-off trench from sta. 37+00. Embankment is being placed and hand-compacted on each side of the concrete wall.
Thumbnail for 'View of cut-off trench looking toward right abutment'
Format:
Image
View of cut-off trench looking toward the right abutment of the dam from the upstream rim of the cut-off trench opposite station 33+50. Refer to Pine R - 71
Thumbnail for 'Cut-off trench, looking toward right abutment'
Format:
Image
Cut-off trench, looking toward right abutment from sta. 33+50.
Thumbnail for 'Compacting embankment'
Format:
Image
Compacting embankment adjacent concrete cut-off wall, with air-operated sheet-piling hammers.
Thumbnail for 'Looking toward right abutment in cut-off trench'
Format:
Image
Looking toward right abutment in cut-off trench. Part of footing for concrete wall is seen on slope. Wagon drill is working on 50-foot grout hole. Refer to Pine R - 66.
Thumbnail for 'Survey crew in deepest portion of cut-off trench'
Format:
Image
Cut-off trench excavation looking toward left abutment from a point opposite sta. 27+50. Survey crew is seen working at deepest portion of trench, which was through the sand pocket at station 23+25.
Thumbnail for 'Placing concrete in cut-off wall'
Format:
Image
Placing concrete in cut-off wall opposite station 33+50, looking toward the right abutment. At left center concrete from the pump-crete pipe line is flowing into a hopper from which it is wheeled in buggies to the point of placement.
Thumbnail for 'View of right abutment along centerline'
Format:
Image
Looking toward the right abutment along centerline of the cut-off trench from opposite dam axis sta. 30+50, cut-off wall is completed, and placing of hand-compacted embankment has been started.