Thumbnail for 'Looking upstream from top of embankment'
Format:
Image
Looking upstream from top of embankment at sta. 1+00. The slope at left foreground is ready for riprap. Note shoulder at right where riprap abuts the road ramp constructed by the contractor, which will be left to form a blanket at the left abutment.
Thumbnail for 'Placing dumped riprap on upstream slope of embankment'
Format:
Image
Placing dumped riprap on upstream slope of embankment in vicinity of sta. 33+00. Dragline is being used to grade material to the required slope.
Thumbnail for 'Looking along upstream slope of dam'
Format:
Image
Looking along upstream slope of dam from station 2+00 toward right abutment . Some hand placing is being done, to bring the riprap to grade. Note stockpile of riprap along crest of dam for use after parapet wall is placed.
Thumbnail for 'Looking downstream from point on right side of river (2)'
Format:
Image
Looking downstream in river section from point on waste pipe on right side of river. End of left half of the permanent cofferdam is seen back of the tripod. Refer to Pine R - 83.
Thumbnail for 'Looking downstream from point on right side of river (1)'
Format:
Image
Looking downstream in river section from point on waste pipe on right side of river. Foundation for a portion of the cofferdam is seen at extreme left.
Thumbnail for 'Looking toward left abutment'
Format:
Image
Looking toward left abutment from sta. 14+60 in cut-off trench. Excavation for trench across the river is complete and ready for refilling.
Thumbnail for 'Looking toward right abutment'
Format:
Image
Looking toward right abutment in bottom of cut-off trench from sta. 8+50. Dragline is removing timbers from Test Pit No. 11.
Thumbnail for 'View of cofferdam'
Format:
Image
View of cofferdam looking upstream from a point 115 feet downstream from axis at station 13+00.
Thumbnail for 'View from opposite station of left abutment'
Format:
Image
View from opposite station 16+00 looking toward left abutment. The partially excavated secondary cut-off trench is seen in the distance. The primary cut-off trench is in the middle background.
Thumbnail for 'View of right abutment along upstream cofferdam face'
Format:
Image
Looking along the upstream face of the permanent cofferdam toward the right abutment. The trucks and Le Tourneaus are on top of the temporary cofferdam, wasting sand from embankment stripping to fill the spade between the two dams.
Thumbnail for 'Looking toward left abutment (1)'
Format:
Image
Looking toward left abutment along alignment of secondary cut-off trench from axis station 16+00. The trench has been refilled with compacted embankment in foreground.
Thumbnail for 'Looking toward left abutment (3)'
Format:
Image
Looking toward left abutment from station 16+50. Placing impervious embankment in old river channel.
Thumbnail for 'Looking toward left abutment (2)'
Format:
Image
Looking toward left abutment from end of secondary cut-off trench opposite station 16+50, showing embankment placing operations in old river channel.
Thumbnail for 'Placing sewer pipe toe drain'
Format:
Image
Placing the 12-inch diameter sewer-pipe toe drain. The boards were used to gauge the 6 inches of 3/4-inch to 1.5-inch gravel required to be placed about the pipe. The remainder of the trench was filled with small cobbles.
Thumbnail for 'Example of filter blanket fill'
Format:
Image
Material seen in foreground shows the type of material that is being placed in the 18-inch filter blanket at downstream toe of dam. Cobbles are in the cobble-fill section.
Thumbnail for 'View of right abutment from center of spillway (1)'
Format:
Image
Looking toward right abutment from axis.
Thumbnail for 'View of right abutment from center of spillway (2)'
Format:
Image
Looking toward right abutment from axis.
Thumbnail for 'Looking at downstream slope of embankment'
Format:
Image
Looking at downstream slope of embankment from a point in the old river channel about 600 ft. downstream from axis. Slope near the crest of the dam has not been graded. Note piezometer well cover at station 11+75 in center of picture.
Thumbnail for 'View of cut-off trench'
Format:
Image
View of cut-off trench looking toward left abutment from opposite station 15+50, showing sand deposits being removed. Refer to Pine R - 121.
Thumbnail for 'Looking toward right abutment'
Format:
Image
Looking toward right abutment in bottom of cut-off trench from station in 10+50. Note sand deposit on left side.